Monday.  Our eager crew arrives on the jobsite and meets Sithombana "Monica" Dhlamini.  The slab is in place.  The walls need to be complete by the end of the day.
Tuesday.  With the walls complete, we set about to set the trusses, and install purlins.  The walls are "Stipple-creted", and the tiles are loaded onto the roof.
Wednesdays.  The roof crew installs tiles.  An insulation crew puts solid insulation between the joists, and a carpentry crew puts up battens and frames the walls.
Thursday.  Drywall day on the inside.  Finish the roof.  Do electrical work.  Paint trim.
Friday.  Paint and spruce up.  Set the doors.  Plant a tree.  Get a host of little things done.